Saturday, June 11, 2011
Decking's Complete, Tiling's 99% there and Fittings and Electrical have started
Well so close now, only a few more weeks. Walk through is booked for the 20th of June. Decking has been completed, Tiling is almost there, just the final touches and the fire place left! Electrical has started and we've purchased our feature chandeliers for the free form (lights are expensive and don't even get me started on the globes! Candles I think are the way of the future!
Sunday, May 29, 2011
Decking's begun, Front Window's complete and My New Toy!
Yep, that's it my new toy - a fold out ironing board :)
Guest Bedroom - Tiling Complete
Decking - the beginnings of the parents retreat!
The planting has begun - meet the peppermint tree
Papaya Tree mmmmm!
Keep growing grass!
Tuesday, May 24, 2011
Halfway Through Tiling and Garage Doors are in!
The tiler is half way through, tiling really is an art, the patience they must have! Garage doors were fitted today and downpipes and fascias have had their first coat of paint. The front window is finally in, and looking good! The shed has also been approved by council which is good news! But most of all the grass is growing!

Friday, May 13, 2011
House is at Lock Up Stage
Plastering, Ceilings, Windows, Cabinetry and Benchtops are complete and we're now into the finer details. Tiling is due to be finished in three weeks and our expected handover date is end of June. Hmmmmmm still lots to do!
- Appliances
- Airconditioning
- Fire place
- Showers, Taps & Toilets
- Electrical
- Garage Doors
- Door handles
- Decking
- Balustrading
- Painting and Staining
- Appliances
- Airconditioning
- Fire place
- Showers, Taps & Toilets
- Electrical
- Garage Doors
- Door handles
- Decking
- Balustrading
- Painting and Staining
kitchen
powder room
second bathroom
kitchen
washroom - garage
laundry
ensuite
ensuite
guest bathroom
Friday, March 11, 2011
Roof complete, Verandahs are up and Plastering has started!
The roof and verandahs are now up. The wood has been stained and plastering is on it's way to completion. Ceiling arrived today!
It's looking good, just like a home rather than a construction site. So close but still so far away,
well it feels like it anyway. Really hanging out to move in now!
It's looking good, just like a home rather than a construction site. So close but still so far away,
well it feels like it anyway. Really hanging out to move in now!
Wednesday, January 12, 2011
Walls are done and roof has commenced!
Unfortunately having the roof completed by Christmas was a little eager, but needless to say it’s progressing well.
The house was definitely high on topics of conversation over the Christmas break. Which in our case always seems to lead to more money.
From increasing the wall tiling, to upgrading basins and additional electrical, a very expensive conservation indeed.
On a different note, we seem to be growing watermelons.